SCH Number 2015091009
Project Info
- Title
- Zone E Recycled Water System Expansion
- Description
- The proposed project would include construction of approximately 8,000 ft (1.5 miles) of recycled water pipelines within an SMWD easement, SMWD property, and beneath existing roadways. The pipelines would range in size from 4 to 8 in. The pipelines would require excavation depths of approximately 5.5 ft within the existing easement and road rights-of-way. Once completed, the anticipated amount of recycled water would be approximately 70 acre-ft per year. The project also includes the construction of approximately 1,300 ft of a 4-in or smaller force main for future construction of a lift station located on the SMWD Upper Oso Reservoir property.
2 documents in project