Zone E Recycled Water System Expansion MND

2 Documents in Project

Summary

SCH Number
2015091009
Lead Agency
Santa Margarita Water District
Document Title
Zone E Recycled Water System Expansion MND
Document Type
NOD - Notice of Determination
Received
Posted
10/26/2015
Present Land Use
Z: RPD-14, R, CF, O'Neill Regional Park, RS-5000 PD(10000)(SR); GPD: Res. 14, Rec./OS, CF, Reg. OS, Sub. Res.
Document Description
The proposed project would include construction of approximately 8,000 ft (1.5 miles) of recycled water pipelines within an SMWD easement, SMWD property, and beneath existing roadways. The pipelines would range in size from 4 to 8 in. The pipelines would require excavation depths of approximately 5.5 ft within the existing easement and road rights-of-way. Once completed, the anticipated amount of recycled water would be approximately 70 acre-ft per year. The project also includes the construction of approximately 1,300 ft of a 4-in or smaller force main for future construction of a lift station located on the SMWD Upper Oso Reservoir property.

Contact Information

Name
Don Bunts
Agency Name
Santa Margarita Water District
Contact Types
Lead/Public Agency

Location

Cities
Mission Viejo, Rancho Santa Margarita
Counties
Orange
Cross Streets
Meadow Ridge Drive and Chrisholm Trail
Zip
92676
State Highways
SR 18, 19, 241
Schools
Portola Hills ES
Waterways
Upper Oso Reservoir
Township
6S
Range
7W
Section
9
Base
SBB&M

Notice of Determination

Approving Agency
Santa Margarita Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print