SCH Number 2011089005


Project Info

Title
Palmdale Hybrid Power Plant
Description
On July 20, 2015, Palmdale Energy LLC submitted a Petition to Amend the previously approved Palmdale Hybrid Power Project. On Aug. 9, 2017, the Energy Commission approved the Petition to Amend with a Final Decision. This Committee-assigned amendment to the previously approved Palmdale Hybrid Power Project changes the project to a natural-gas-fired combined-cycle power plant with an approx. net output of 699.4 MW. The approval reduces the site to 50 acres, eliminates the solar component and replaces the combustion turbine technology with fast start flexible technology.
Download CSV New Search

 

3 documents in project

Type Lead/Public Agency Received Title
California Energy Commission Palmdale Energy Project
California Energy Commission Approval of Inter-District Transfer of 150 tpy NOx ERC's from MDAQMD and 60 tpy of VOC ERCs from SJVUAPCD to the AVAQMD pursuant to Health & Safety Code (H&S Co
California Energy Commission Palmdale Hybrid Power Plant