Title
Construction and Operation of New Drinking Water Reservoir and Transmission Line
Description
Golden State Water Company will install a 0.5 MG water storage tank and ~1820 linear ft of 12 inch transmission line to serve the community of Wrightwood. The water tank will be built on a concrete pad and will measure 64 ft in diameter and be 24.5 ft in height. The waterline will be installed beginning at the intersection of Linnet Road and Elm Street and will continue through the Wrightwood Methodist Camp up to the new tank site. An 8 ft security fence will be installed around the site for security purposes.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
California Department of Public Health (CDPH) Construction and Operation of New Drinking Water Reservoir and Transmission Line
California Department of Public Health (CDPH) Construction and Operation of New Drinking Water Reservoir and Transmission Line