- Description
- A Conditional Use Permit and Development Review application requesting to construct and operate a new public utility facility functioning as a battery energy storage system (BESS). The proposed facility would Include the pIacement of 172 battery energy storage enclosures and associated electrical equipment, including 43 medium voltage transformers. The project would connect to the adjacent Southern California Edison (SCE) substation to provide additional capacity to the electrical grid.