Pipeline Improvements for Bell Recharge Project
Description
Installation of a new, 1-mile-long, Class 125, 21-inch bi-directional PVC pipe within the Kern County road right-of-way (ROW) along Merced Avenue and Mannel Avenue. The new bi-directional pipeline would connect the north and south systems and facilitate water movement through the District. The pipeline would also connect to three existing turnouts west of Mannel Avenue (1.7-1.5-8, 1.7-1.5-10, and 1.7-1.5-12) and another existing 15-inch pipe section of Lateral 134.4-1.7S-1.5E, west of Mannel Avenue. The proposed project would also increase the capacity of an existing pump station (from 3 cfs to 10 cfs) on Beech Avenue.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
Shafter-Wasco Irrigation District Pipeline Improvements for Bell Recharge Project
Shafter-Wasco Irrigation District Pipeline Improvements for Bell Recharge Project