SCH Number 2020039052


Project Info

Title
Hummingbird Energy Storage Project
Description
Conditional Use Permit to allow an energy storage facility in an existing approximately 102,462 square foot industrial building with a new approximately 15,000 square foot substation on a 25.33 gross acre site. The energy storage facility and associated substation would connect to the Metcalf Substation via a 2.5- mile-long, underground transmission line within the Monterey Road public right-of-way. No permanent employees would occupy the building.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
City of San Jose Hummingbird Energy Storage Project (Lake or Streambed Alteration Agreement No. EPIMS-SCL- 15156-R3)
City of San Jose Hummingbird Energy Storage Project