SCH Number 2019120617


Project Info

Title
Santa Clarita-Valencia Interconnection Piping
Description
The purpose of the project is to interconnect the water agency's distribution system piping to improve efficiency of water delivery. The project involves temporary construction within the public right of way consistent with City of Santa Clarita traffic control requirements. Construction will take place over 14 days and include limited excavation and a pipeline connection between Santa Clarita Valley Water Agency's Santa Clarita Water Division and Valencia Division water lines. The newly installed pipeline will be 10 inches in diameter and approximately 50 feet long.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
Santa Clarita Valley Water Agency Santa Clarita Valley Water Agency (SCVWA) - Valencia Division: 10-lnch Interconnection with SCVWA - Santa Clarita Division (Project)
Santa Clarita Valley Water Agency Santa Clarita-Valencia Interconnection Piping