SCH Number 2019119034


Project Info

Title
San Quentin Pump Station Replacement Project
Description
Project plans involve replacement of the deteriorated San Quentin Pump Station, demolition of the existing station, and improvements to the outfall pipe that extends from the pump station to San Rafael Bay. Development of the new pump station requires removal of existing corrugated metal pipe, riprap rock, base rock, and asphalt and concrete pavement directly to the south of the existing station. This would be followed by installation of a concrete slab to be placed partially over the area of removed rock and concrete adjacent to the existing station. Once the new pump station is operational, the existing station would be removed and disposed of. The deteriorated outfall pipe would then be improved mainly via slip lining. Construction of the proposed project would last for approximately 33 weeks. All improvements would be made within the existing City right-of-way and staging would occur on-site.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
City of San Rafael San Quentin Pump Station Replacement Project
City of San Rafael San Quentin Pump Station Replacement Project