Project Info
- Title
- Carbon Capture and Mineralization Project
- Description
- Note: Review Per Lead The proposed project, consists of a carbon capture and mineralization pilot facility that would operate for a 12-month period. The facility would remove carbon dioxide (CO2) from a slipstream of flue gas from Calpine's Los Medanos Energy Center or an outlet stream of gas from the gas-fired steam boiler and combine the removed CO2 with locally sourced demolished/returned concrete to produce new "CO2 sequestered" and "upcycled" rock products. These products would be sold to Bay Area businesses, governments and consumers for use in a wide range of low carbon and high-performance concrete applications. The project site has been previously disturbed and permanently capped. Construction of the project would consist of skid-mounted equipment with no below grade construction activities of facilities or pipelines.
3 documents in project