SCH Number 2018091006
Project Info
- Title
- Power Line Safety Maintenance
- Description
- The proposed project involves performing powerline maintenance to increase the ground to conductor clearance under a portion of the PG&E Moss Landing-Metcalf 500 kV overhead transmission line to ensure public safety, increase reliability, and meet Federal minimum vertical clearance from power line to ground. The project is comprised of grading activities requiring cut of approx 106 cy over an area of approx 895 sf with a depth that ranges from approx 1 ft to 6 1/2 ft. Cut is proposed to be hauled off site, except from the top 6 in of top soil which would be stockpiled on a plastic tarp to isolate it from weed seed, then redistributed over the disturbed area and seeded with local seed stock.
2 documents in project