SCH Number 2018072071


Project Info

Title
Recirculated Draft EIR for Estrella Substation and Paso Robles Area Reinforcement Project
Description
The proposed project involves the construction of a 230 kV/70 kV substation, a 230 kV transmission line interconnection, a new 70 kV double-circuit powerline between the new 70 kV substation and the existing San Miguel-Paso Robles 70 kV power line, and reconductoring of the existing San Miguel-Paso Robles 70 kV power line. The draft EIR was originally circulated for public review on December 8, 2020 and the public review and comment period lasted until February 22, 2021. Comments received on the draft EIR from Horizon West Transmission, Adams Broadwell Joseph & Cardozo, and Pacific Gas & Electric Company have necessitated recirculation of portions of the draft EIR. Specifically, the following portions of the draft EIR are being recirculated: Chapter 2, “Project Description;” Section 4.2, “Agricultural Resources;” and Section 4.3, “Air Quality.”
Download CSV New Search

 

3 documents in project

Type Lead/Public Agency Received Title
California Public Utilities Commission (CPUC) Recirculated Draft EIR for Estrella Substation and Paso Robles Area Reinforcement Project
California Public Utilities Commission (CPUC) Estrella Substation and Paso Robles Area Reinforcement Project
California Public Utilities Commission (CPUC) Estrella Substation and Paso Robles Area Reinforcement Project