Estrella Substation and Paso Robles Area Reinforcement Project

4 Documents in Project

Summary

SCH Number
2018072071
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Estrella Substation and Paso Robles Area Reinforcement Project
Document Type
NOD - Notice of Determination
Received
Posted
4/25/2024
Document Description
The project involves the construction of a 230 kilovolt (kV)/70 kV substation (Estrella Substation), a 230 kV transmission line interconnection, a new 70 kV double-circuit powerline, and reconductoring of the existing San Miguel-Paso Robles 70 kV power line. The Environmentally Superior Alternative was selected, which includes the Estrella Substation, Alternative PLR-1A (Estrella Route to Estrella Substation), and Alternatives BS-2 (Battery Storage to Address Distribution Objective) and BS-3 (Behind-the-Meter Solar and Battery Storage). Alternatives BS-2 and BS-3 shall be implemented via the CPUC's Distribution Investment Deferral Framework process, as outline in the decision.

Contact Information

Name
Trevor Pratt
Agency Name
California Public Utilities Commission
Job Title
Senior CEQA Project Manager
Contact Types
Lead/Public Agency

Location

Cities
Paso Robles
Counties
San Luis Obispo
Regions
Citywide, Countywide, Southern California, Unincorporated
Cross Streets
various
Zip
93446
State Highways
Highway 101, State Route 46
Airports
Paso Robles Municipal Airport
Schools
various
Waterways
various

Notice of Determination

Approving Agency
California Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print