- Cross-Town Water Pipeline Project
- Description
- Project consists of a new 8,065 linear feet, 20 inch diameter buried water pipeline which would connect the discharge pipeline from the Steckel Water Conditioning Facility at the Steckel Drive/Santa Barbara Street intersection to the Pleasant Street/Tenth Street intersection. By linking the Steckel Water Conditioning Facility to both the Main Reservoir and the Gooding Tank the project would increase operational efficiency. The project would be installed by open trench methods (trenching, pipe bedding, pipe installation, backfill, pavement repair), excluding the Fagan Barranca pipeline crossing which would be installed using trenchless methods. In addition, the project would include three smaller new potable water and storm water pipelines.