SCH Number 2007092077


Project Info

Title
Schapiro Reservoir Replacement Project
Description
Construction of a new 1.0-MG reservoir at the existing reservoir location between Bonita Road and Capital Hill Avenue; installation of a 40-foot diameter temporary tank on the reservoir site during construction of the new reservoir; construction of a new regulator on the Pearl Pumping Plant site on North Arlington Boulevard; construction of a new 320-foot, 16-inch diameter inlet/outlet pipeline between the proposed 1.0-MG tank and the new reservoir valve pit at the Pearl Pumping Plant site; and installation of a seismic isolation valve within the new valve vault at the Pearl Pumping Plant site.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
East Bay Municipal Utility District (EBMUD) Schapiro Reservoir Replacement Project
East Bay Municipal Utility District (EBMUD) Schapiro Reservoir Replacement Project