Schapiro Reservoir Replacement Project

2 Documents in Project

Summary

SCH Number
2007092077
Lead Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Schapiro Reservoir Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
11/30/2007
Present Land Use
Water reservoir and pumping plant site
Document Description
Construction of a new 1.0-MG reservoir at the existing reservoir location between Bonita Road and Capital Hill Avenue; installation of a 40-foot diameter temporary tank on the reservoir site during construction of the new reservoir; construction of a new regulator on the Pearl Pumping Plant site on North Arlington Boulevard; construction of a new 320-foot, 16-inch diameter inlet/outlet pipeline between the proposed 1.0-MG tank and the new reservoir valve pit at the Pearl Pumping Plant site; and installation of a seismic isolation valve within the new valve vault at the Pearl Pumping Plant site.

Contact Information

Name
John Hurlburt
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Richmond, San Pablo
Counties
Contra Costa
Cross Streets
Bonita Road and Capitol Hill Avenue
Zip
94806
Total Acres
1.8
Parcel #
193-152-003
State Highways
24
Schools
Riverside ES, Bayview ES, Dover ES, Helms MS

Notice of Determination

Approving Agency
East Bay Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.