SCH Number 2006042089
Project Info
- Title
- Rocky Point Erosion Control Project, Phases 3 & 4
- Description
- Construct erosion control improvements within a 78-acre area bordered on the west by Aspenwalk Road, on the north by Primrose Road and Midway Avenue, on the east by Rocky Point Road, and on the south by Keller Road. Erosion control improvements include soil and vegetation restoration, stormwater treatment basins, infiltration chambers, boulder parking barriers, rolled curb and gutter, stormdrain pipe, drop inlets, manholes, sediment traps, AC swales, AC berms, and cobble swales. The planned improvements will be constructed in the City right of way, on public land, and privately owned parcels that will be acquired by the City or where easements will be purchased. Approximately 132 trees (60 smaller than 10 inches diameter at breast height (dbh) and 72 trees 10 inches dbh or greater) will be removed. No trees larger than 24 inches dbh will be removed.
2 documents in project