Flume Creek CAPM
Summary
SCH Number
2024120559
Lead Agency
California Department of Transportation, District 2
(DOT)
Document Title
Flume Creek CAPM
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
State Highway
Document Description
The California Department of Transportation, using federal and state funding, proposes to rehabilitate Interstate 5 (I-5) through repaving activities, structural repairs, drainage improvements, and construction of supporting infrastructure. The limits of work occur between post miles 58.0 and 67.019 in Shasta County, and post miles 0.0 and 2.7 in Siskiyou County.
The proposed project would include the following improvements:
Roadway Improvements
• Overlay activities – rubberized hot-mixed asphalt
o Overlay roadway, including the shoulders and median
o Conform on- and off-ramps
o Perform digouts at various locations
• Install shoulder backing to support edge of pavement
• Repair approximately 100 rocking concrete slabs
• Seal parking area at PM 62.36
Structures
Project implementation would include rehabilitation of the Castle Creek Bridge (PM 63.31) and Castella Bridge (PM 63.58) as follows:
• Install a 4.5-inch reinforced concrete 'deck-on-deck' with a 1-inch polyester
concrete overlay
• Upgrade the existing bridge railing
• Replace the existing median barrier
• Construct new approach slabs
Signs and Delineation
• Upgrade/replace signs to current standards.
• Install/apply recessed retroreflective pavement markers, as well as sprayable
thermoplastic pavement striping/marking throughout the project corridor.
Traffic Safety
• Replace metal beam guardrail with Midwest Guardrail System steel-post
guardrail in-place, and transition railing at bridge sites.
• Remove and replace approximately 11 miles of median barrier. The current
median barrier height varies between 26 and 35 inches. To meet current
standards, the median barrier height would be increased to 42 inches.
Transportation Management Systems
Upgrade the existing Road Weather Information System and Closed-Circuit Television stations in the community of Dunsmuir (PM 2.61). Replace ±30 damaged loops at the existing traffic monitoring stations.
Lighting
As part of the proposed project, seven new luminaires would be installed, and 13 luminaires replaced along various off-ramps. Luminaire installation would include minor trenching to provide power. The lighting locations/improvements are summarized in Table 1.
Table 1. Proposed Lighting Improvements
Luminaire Location Replace Add
Flume Creek Road - Northbound off-ramp 1 1
Conant Road - Southbound off-ramp 1 1
Sweetbrier Avenue - Northbound off-ramp 1 1
Sweetbrier Avenue - Southbound off-ramp 1 1
Castella - Northbound off-ramp 2 -
Castella - Southbound off-ramp 1 1
Soda Creek Road - Northbound off-ramp 1 1
Soda Creek Road - Southbound off-ramp 1 1
Crag View Drive - Northbound off-ramp 2 -
Central Dunsmuir - Northbound off-ramp 2 -
Total: 13 7
Disposal/Borrow Sites
Project implementation would include approximately seven acres of ground disturbance; with a maximum excavation depth estimated at 10 feet. Excess soil material and construction debris would become the property of the contractor. No disposal and/or borrow sites are proposed.
Drainage Improvements
As part of the proposed project, drainage improvements, consisting of culvert installation/replacement, liner installation, drainage inlet replacement, headwall installation, and downdrain replacement, would be performed on 81 drainage systems. Additionally, various drainage inlets may need to be adjusted to grade. Further, culvert replacement activities may necessitate temporary clearwater diversions. The proposed drainage improvements would require vegetation removal. A detailed description of the proposed drainage improvements is provided below in Table 2 (see Initial Study). Culvert systems are often comprised of multiple segments, which are separated by drainage inlets or other structures. Culvert segments subject to replacement, including the number of drainage inlets are identified in the table.
Slope Stabilization
To address minor settling in the northbound lane at PM 1.1 in Siskiyou County, the roadway would be excavated and stabilized through construction of a geosynthetic reinforced embankment (GRE). The roadway would be excavated and backfilled in alternating horizontal layers of fill soil and geosynthetic reinforcement. The layers would extend up to the structural portion of the roadway. A drainage system would be included in the GRE.
Wildlife Management
Wildlife Crossing
A 12-foot-wide by 12-foot-tall reinforced concrete box culvert would be installed at PM 65.88 via cut and cover to allow wildlife to safely cross the highway.
Wildlife Fencing
An eight-foot-tall chain-link fence or other applicable fence type would be installed to direct wildlife under I-5. Wildlife fencing would be installed in conjunction with the proposed wildlife crossing. The estimated limits are included below.
• West of Highway—PMs 65.45 to 66.17
• East of Highway—PMs 65.45 to 66.10
To improve safety for animals and the traveling public, fence installation would include jump outs and/or deer gates, while the median barrier would include intermittent gaps along the length to allow wildlife to exit the roadway. Both elements would reduce the potential for wildlife to become trapped on the highway. Additionally, the fence design would include vehicle and/or pedestrian gates to accommodate maintenance activities.
New Impervious Area
The new impervious area is estimated at 0.01 acres.
Staging
Four staging areas have been identified along the project corridor: PMs 60.47 (northbound), 61.65 (northbound), 65.41 (southbound), and 0.95 (southbound).
Utilities
Within the project limits, I-5 supports overhead and underground utilities, including electric and fiber optic lines. Culvert replacement activities at PM 2.65 would require relocating an existing fiber optic line.
Right of Way
Caltrans would acquire temporary construction easements, including right-of-way acquisition at various locations to accommodate project activities.
Traffic Management Project construction would utilize lane and ramp closures as needed.
Schedule
The work would be completed in three construction seasons and would require approximately 360 working days.
Contact Information
Name
Carolyn Sullivan
Agency Name
Caltrans
Job Title
Senior Environmental Planner
Contact Types
Lead/Public Agency / Project Applicant
Phone
Location
Cities
Dunsmuir
Counties
Shasta, Siskiyou
Regions
Northern California
Zip
96025
Other Location Info
Interstate 5, Post Miles 58.0 to 67.019 (Shasta County), Post Miles 0.0 to 2.7 (Siskiyou County)
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Conservation (DOC), California Department of Fish and Wildlife, Northern and Eureka Region 1 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Resources Recycling and Recovery, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 2 (DOT), California Department of Transportation, Division of Aeronautics (DOT), California Department of Transportation, Division of Transportation Planning (DOT), California Department of Water Resources (DWR), California Fish and Game Commission (CDFGC), California Governor's Office of Emergency Services (OES), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Central Valley Redding Region 5 (RWQCB), California State Coastal Conservancy (SCC), California State Lands Commission (SLC), California Transportation Commission (CATC), Central Valley Flood Protection Board, Delta Protection Commission, Delta Stewardship Council, Department of General Services (DGS), Office of Historic Preservation, Sierra Nevada Conservancy, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Water Quality
Development Types
Transportation:Highway/Freeway (Pavement, drainage, and safety improvements on I-5 Hwy rehab)
Local Actions
Site Plan
Project Issues
Aesthetics, Air Quality, Biological Resources, Cumulative Effects, Drainage/Absorption, Energy, Geology/Soils, Greenhouse Gas Emissions, Hazards & Hazardous Materials, Hydrology/Water Quality, Mandatory Findings of Significance, Noise, Public Services, Transportation, Utilities/Service Systems, Wetland/Riparian, Wildfire
Public Review Period Start
Public Review Period End
Attachments
Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.