Suisun Force Main Reliability Project
2 Documents in Project
Summary
SCH Number
2024100427
Lead Agency
Fairfield Suisun Sewer District
Document Title
Suisun Force Main Reliability Project
Document Type
NOD - Notice of Determination
Received
Posted
11/26/2024
Document Description
FSSD is proposing to construct two new parallel force mains to operate in lieu of the existing Suisun Force Main to ensure service reliability. The existing force main would be inspected after the new parallel force mains are installed and either abandoned, repurposed, or rehabilitated as a separate project based on the inspection results. The project would also include installation of appurtenant infrastructure necessary for operation and maintenance of the force mains and stormwater improvements. The project alignment would extend between FSSD’s Suisun Pump Station and Central Pump Station, paralleling the existing alignment where possible, but would follow a different alignment compared to the existing force main.
Contact Information
Name
Karl Ono
Agency Name
Fairfield-Suisun Sewer District
Job Title
Senior Engineer
Contact Types
Lead/Public Agency
Phone
Location
Cities
Fairfield, Suisun City
Counties
Solano
Regions
Countywide
Cross Streets
Civic Center Blvd., Main St., Ohio St., Illinois St., Madison St.
Zip
94585
Total Acres
2
Parcel #
NA
State Highways
State Route 12
Railways
UPPR
Airports
NA
Schools
various
Waterways
Suisun Slough
Notice of Determination
Approving Agency
Fairfield-Suisun Sewer District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Solano
Final Environmental Document Available at
https://www.fairfieldsuisunsewer.ca.gov/sfm/
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.