Spring Creek Road at Fall River Bridge Replacement

3 Documents in Project

Summary

SCH Number
2023030403
Lead Agency
Shasta County
Document Title
Spring Creek Road at Fall River Bridge Replacement
Document Type
NOD - Notice of Determination
Received
Posted
10/30/2024
Document Description
The project entails replacing the existing Spring Creek Bridge (06C0209) over the Fall River with a new bridge on the same alignment. New paved roadway approaches would be installed at both ends of the bridge. Guardrails and signage would be installed, and existing fencing would be replaced. A roadside ditch would be installed on the north side of the bridge to convey drainage away from the road. The existing bridge would be removed during construction of the new bridge.

Contact Information

Name
Jacob Back
Agency Name
County of Shasta
Job Title
Associate Engineer
Contact Types
Lead/Public Agency

Location

Cities
Fall River Mills
Counties
Shasta
Regions
Unincorporated
Cross Streets
McArthur Road to Spring Creek Road
Zip
96067
Total Acres
1.94
Parcel #
Various
State Highways
McArthur Road-A19
Railways
None
Airports
Fall River Mills Airport
Schools
Fall River Elementary
Waterways
Spring Creek, Fall River, Eastman Lake
Township
38N
Range
4E
Section
28
Base
MDM

Notice of Determination

Approving Agency
County of Shasta
Approving Agency Role
Lead Agency
Approved On
County Clerk
Shasta
Final Environmental Document Available at
Shasta County Department of Public Works 1855 Placer St. Redding, CA 96001

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print