The Applicant is proposing to construct approximately 2,750 linear feet of 12-inch Polyvinyl chloride (PVC) water main in Avenue 11, and 2,750 linear feet of 8-inch PVC water main in Mountain View Drive and Adobe Way. The alignment of this water main will be located within the County right-of-way. Any existing water main in Avenue 11 will be abandoned in place. Additionally, new water meters and meter boxes will be installed at 339 properties within the Rolling Hills Water System (RHWS). The improvements will all be incorporated into the existing RHWS, which is currently being fed by three active wells providing safe, clean drinking water.
The Project also includes a full facility refurbishment of the Well No. 2 site, including the well pump and all other well site facilities that have exceeded their life expectancy. The well casing will be sleeved if determined necessary during a well investigation. The Project also includes the addition of cathodic protection to the water storage tank
Contact Information
Name
Abbygayle Britton
Agency Name
State Water Resources Control Board
Job Title
Environmental Scientist
Contact Types
Lead/Public Agency
Phone
Location
Cities
Rolling Hills unincorporated
Counties
Madera
Regions
Unincorporated
Other Location Info
The Project site consists principally of the Rolling Hills unincorporated community within Madera County.
Other Information
The community encompasses an area of approximately 390-acres (0.6 square miles).
Notice of Determination
Approving Agency
State Water Resources Control Board
Approving Agency Role
Lead Agency
Approved On
County Clerk
Madera
Final Environmental Document Available at
A final copy of the IS/MND, the MMRP, comments and responses and the record of
approval for the Project are available to the general public at the State Water Board,
Division of Financial Assistance at 1001 I Street, 16th Floor, Sacramento CA 95814.
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.