Group 3E Storm Drain PPA
4 Documents in Project
Summary
SCH Number
2022030147
Lead Agency
City of San Diego
Document Title
Group 3E Storm Drain PPA
Document Type
NOD - Notice of Determination
Received
Posted
4/2/2025
Document Description
The project will install an approximately 30-foot-long segment of 18-inch diameter reinforced concrete pipe (RCP) storm drain and a new 5-foot by 5-foot curb inlet. This project will use the open trench method of construction. Trenches are typically 3 to 4 feet wide and 5 to 7 feet deep and are dug with excavators and similar large construction equipment. All trenching work would occur entirely within the developed right-of-way. An existing traffic signal conduit and loop detectors will be relocated. Any roadway impacted by trenching will be resurfaced.
Contact Information
Name
Nazie Mansury
Agency Name
City of San Diego
Job Title
Associate Engineer
Contact Types
Lead/Public Agency
Phone
Email
Location
Cities
San Diego
Counties
San Diego
Regions
Citywide, Southern California
Other Location Info
The project is located within the right-of-way at the intersection of West Point Loma Boulevard and Nimitz Boulevard.
Notice of Determination
Approving Agency
City of San Diego
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
Development Services Department, 1222 First Avenue, San Diego, CA 92101.
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.