North Shore Pipeline Replacement Project
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2020040323
- Lead Agency
- San Bernardino County
- Document Title
- North Shore Pipeline Replacement Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/14/2020
- Project Applicant
- PAMELA CHAVEZ- SOUTHWEST GAS CORP
- Document Description
- The project involves upgrading existing high-pressure natural gas pipeline infrastructure along North Shore Lane, North Shore Drive/State Route 38, and Stanfield Cutoff to increase the pressure and natural gas feed into the Big Bear area for the purpose of meeting existing and future demands. The proposed improvements would involve replacing the existing 6-inch high-pressure steel natural gas pipeline with an 8-inch high-pressure steel natural gas pipeline. Other lateral pipelines would also be upgraded. The existing natural gas pipelines would be abandoned in place and capped off, and new natural gas pipelines would be installed primarily by open trench excavation with some areas installed by horizontal directional drilling. The project would require an Encroachment Permit and Construction Permit from the County of San Bernardino; Encroachment Permit from the U.S. Forest Service and California Department of Transportation; Section 1602 Streambed Alteration Agreement from the California Department of Fish and Wildlife; Construction Permit from the City of Big Bear Lake; and a National Pollutant Discharge Elimination System Construction General Permit and Waste Discharge Permit from the Santa Ana Regional Water Quality Control Board.
- Contact Information
-
Jim Morrissey
County of San Bernardino - Land Use Services Department
385 N. Arrowhead Avenue First Floor
San Bernardino, CA 92415-0187
Phone : (909) 387-4234
Jim.Morrissey@lus.sbounty.gov
Location
- Cities
- Community of Bear Valley
- Counties
- San Bernardino
- Regions
- Southern California
- Cross Streets
- State Route 38/North Shore Drive and North Shore Lane
- Zip
- 92314
- Total Acres
- Linear 2.3 miles
- Parcel #
- Not Applicable
- State Highways
- SR-38, SR-18
- Railways
- None
- Airports
- Big Bear Airport
- Schools
- Various
- Waterways
- Big Bear Lake
- Township
- 2N
- Range
- 1E
- Section
- 17
- Base
- Sn Bndo
Notice of Determination
- Approving Agency
- County of San Bernardino
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- County of San Bernardino 385 North Arrowhead Avenue, First Floor San Bernardino, CA 92415
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- Yes
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Attachments
- Notice of Determination
- PER_2020_00008_NOD PDF 218 K
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.