E Reservoir Replacement and Pump Station
2 Documents in Project
Summary
SCH Number
2020039069
Lead Agency
Vista Irrigation District
Document Title
E Reservoir Replacement and Pump Station
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2020
Document Description
In accordance with its 2017 Potable Water Master Plan (VID 2018), the Vista Irrigation District (VID) is proposing the replacement of the existing oval shaped, partially buried, 1.5-milliongallon (MG) E Reservoir with a new reservoir and construction of a new pump station (proposed project). The proposed project would implement an adopted plan for facility improvements. The Potable Water Master Plan identified seven projects along with their cost estimates in their Capital Improvement Program, including all components of the proposed project. These projects would allow VI D to provide service to the expected 158,627 people that the service area is expected to contain by 2040. The project is located on a 1.88-acre property comprised of one parcel (Assessor's Parcel Number 174- 240-33) located at 2558 Edgehill Road in unincorporated County of San Diego, California, just east of the City of Vista. The new reservoir would increase storage capacity and provide VID with a facility that meets applicable current codes and standards. The new pump station would provide a redundant water supply to higher-pressure zones within VI D's service area when disruptions occur to primary water supplies. The project would require the demolition of the existing E Reservoir and accessory facilities. Within a similar footprint, the proposed project would construct a cast-in-place hexagonal shaped structure that would increase the on-site capacity to approximately 2.92 MG, which is a 1.42 MG net increase. The hexagonal shape would allow for more easily maintained water quality. The proposed project would also construct a new water pump station. The pumps, control panel, and other electric and supervisory control and data acquisition (SCADA) equipment would be housed in an aboveground structure with approximate dimensions of 20 feet by 38 feet that would match the architectural features of the existing adjacent pressure reducing station (PRS) facility.
Contact Information
Name
Greg Keppler
Agency Name
Vista Irrigation District
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Vista Irrigation District
Contact Types
Project Applicant
Location
Counties
San Diego
Parcel #
174-240-33
Other Location Info
Edgehill Road, San Diego County, 92084
Notice of Determination
Approving Agency
Vista Irrigation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.