Southern California Edison Alhambra Warehouse Project

2 Documents in Project

Summary

SCH Number
2020039065
Lead Agency
Alhambra, City of (City of Alhambra)
Document Title
Southern California Edison Alhambra Warehouse Project
Document Type
NOD - Notice of Determination
Received
Posted
6/23/2020
Project Applicant
Southern California Edison
Present Land Use
Industrial

Document Description
Southern California Edison (SCE) is an electricity company that provides electricity and energy for clients throughout Southern California and owns and operates a 35-acre regional operating facility in Alhambra, California. The objective of the proposed Southern California Edison Alhambra Warehouse Project ("Project") is to consolidate storage materials and associated staff from Buildings C, D, and E into a proposed new warehouse. This would better optimize the function and operation of the aged campus, which was built in the 1930s. The Project would include demolition of the approximately 3.3 acres of asphalt and concrete ground cover and the construction of a new approximately 54,000 square foot (SF) warehouse on current yard space bounded by Mission Road and S. Raymond Avenue, in the southwestern corner of the SCE site. Additionally, a new site access gate is proposed at the intersection of S. Raymond Avenue and Chestnut Street.

Contact Information
Paul Lam
City of Alhambra
111 S First Street
Alhambra, CA 91801

Phone : (626) 570-5034
plam@cityofalhambra.org

Location

Cities
Alhambra
Counties
Los Angeles
Cross Streets
S Marengo Ave and W Mission Rd

Notice of Determination

Approving Agency
City of Alhambra
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
City of Alhambra Community Development Department, 111 S. First Street Alhambra, CA 91801

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Final Document(s)
Final_IS_MND_SCEAlhambra_Signed_06212020_text recognized   PDF 17721 K
Notice of Determination
NOD_SCEAlhambraWarehouseProject_text_recognized   PDF 176 K

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print