Revised Interim Measures Implementation Plan, Polynt Composites USA

3 Documents in Project

Summary

SCH Number
2018101005
Lead Agency
Department of Toxic Substances Control
Document Title
Revised Interim Measures Implementation Plan, Polynt Composites USA
Document Type
NOD - Notice of Determination
Received
Posted
3/4/2019
Present Land Use
Manufacturing/M
Document Description
The DTSC has approved the Revised IMIP for soil and groundwater contamination at the Polynt Composites USA, INC. facility located at 2801 Lynwood Road, Lynwood, LA County, CA. The Revised IMIP will expand the existing soil vapor extraction system with the additional air sparging to improve the rate of soil and ground water contaminant removal. The proposed approach will introduce fresh air into the ground wart resulting in physical removal and biological degradation (destruction) of contaminants. Additional soil vapor extraction wells will remove contaminated soil vapor from the soil. *SEE NOD FOR FULL DETAILS.

Contact Information

Name
Paul Ruffin
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Lynwood
Counties
Los Angeles
Cross Streets
Lynwood Rd, Alameda St, Bellinger St
Zip
90262
Total Acres
4.5
Parcel #
6169-010-003
State Highways
I-105
Railways
Var
Schools
Var
Waterways
Compton Creek
Township
3S
Range
12W
Section
10
Base
SB
Other Location Info
2801 Lynwood Road, Lynwood, CA 90262

Notice of Determination

Approving Agency
DTSC
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.