Mt. San Antonio College Transit Center

2 Documents in Project

Summary

SCH Number
2018091026
Lead Agency
Mt. San Antonio Community College
Document Title
Mt. San Antonio College Transit Center
Document Type
NOD - Notice of Determination
Received
Posted
12/24/2018
Present Land Use
GPD: School and public institutional; Z: Mt. SAC Community College with Civic Center Overlay and underlying zoning of RPD - 61,700 - 0.6 DU
Document Description
The proposed project is divided into four project elements. The first element, a new transit center, involves the construction of a ten-bus bay transit center. The bus bays would be located around a central bus plaza and would accommodate pedestrian loading and unloading. Construction of the transit center would include other improvements including improvements to vehicular and non-vehicular circulation; landscape, hardscape, fencing, and lighting; and utility infrastructure. The second element, proposes improvements to Temple Ave including a traffic signal at the existing driveway on Temple Avenue. As part of the third element, the existing vehicular access southeast of Technology Center (Building 28A/B) and between the driveway from Lot D-2 and D-3 would be modified to prohibit vehicular movement. This would involve repaving and adding a series of bollards to restrict through vehicular movement. The last project element would expand the driveway and pedestrian circulation area at the existing driveway that connects the surface parking area to the Exercise Science/Wellness Center (Building 27A). Pool, Pool Building (Building 27B) and Physical Education Center (building 27C) to Modulars 18A through 18D.

Contact Information

Name
Gary Nellesen
Agency Name
Mt. San Antonio Community College
Contact Types
Lead/Public Agency

Location

Cities
Walnut
Counties
Los Angeles
Cross Streets
Bonita Dr/Temple Ave
Zip
91789
Total Acres
1.8
State Highways
I-10, SR 57
Railways
UPRR
Schools
Cal Poly Pomona, International Polytechnic HS, Suzanne MS, Colle
Other Information
wood ES, Leonard G. Westhoff ES

Notice of Determination

Approving Agency
Mt. San Antonio College Community College District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.