Cucamonga Creek Basin 6, 7 and 8 Maintenance and Operation
3 Documents in Project
Summary
SCH Number
2017081006
Lead Agency
San Bernardino Flood Control District
Document Title
Cucamonga Creek Basin 6, 7 and 8 Maintenance and Operation
Document Type
NOD - Notice of Determination
Received
Posted
8/31/2018
Present Land Use
retention basin and groundwater recharge/open space/ open space
Document Description
The California Department of Fish and Wildlife has executed Streambed Alteration Agreement number 1600-2017-0148-R6, pursuant to section 1602 to Fish and Game Code to San Antonio Water Company. The Basin 6 Infiltration Restoration project includes the one time dewatering and desilting of sub-basin A3 of Basin 6 in order to allow for increased groundwater recharge capability. Dewatering includes pumping and discharging water downstream into Basins 7 and 8, then into the confluence with Cucamonga Creek channel. Soils will be tested for permeability through drilling and trenching within the basin bottom. San Antonio Water Company shall not disturb any habitat or vegetation above the 1510 foot elevation in its desilting and recharge efforts. The basin floor will be ripped to a depth of minimum 12 inches as determined by the geotechnical consultant, and then smoothed. All side slopes will be track-walked with heavy equipment in an up and down matter that is approved to break up hardened surface of the uppermost layer.
Contact Information
Name
Claire Ingel
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Upland
Counties
San Bernardino
Cross Streets
Campus Avenue and Colonies Parkway
Zip
91786
Total Acres
+/- 67
Parcel #
104-464-158,-123,-161
State Highways
Sr 66, east of SR 83, SR 210
Airports
Cable Airport
Waterways
Cucamonga Creek Channel
Township
T1N
Range
R7W
Section
20
Base
SBBM
Other Information
I-15
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.