The California Department of Fish and Wildlife has executed Streambed Alteration Agreement number 1600-2017-0148-R6, pursuant to section 1602 to Fish and Game Code to San Antonio Water Company. The Basin 6 Infiltration Restoration project includes the one time dewatering and desilting of sub-basin A3 of Basin 6 in order to allow for increased groundwater recharge capability. Dewatering includes pumping and discharging water downstream into Basins 7 and 8, then into the confluence with Cucamonga Creek channel. Soils will be tested for permeability through drilling and trenching within the basin bottom. San Antonio Water Company shall not disturb any habitat or vegetation above the 1510 foot elevation in its desilting and recharge efforts. The basin floor will be ripped to a depth of minimum 12 inches as determined by the geotechnical consultant, and then smoothed. All side slopes will be track-walked with heavy equipment in an up and down matter that is approved to break up hardened surface of the uppermost layer.

Contact Information
Claire Ingel
CDFW
3602 Inland Empire Blvd
Ontario, CA 91764

(909) 484-0167

Location

Coordinates
34°07'46.4"N 117°38'"W
Cities
Upland
Counties
San Bernardino
Cross Streets
Campus Avenue and Colonies Parkway
Zip
91786
Total Acres
+/- 67
Parcel #
104-464-158,-123,-161
State Highways
Sr 66, east of SR 83, SR 210
Airports
Cable Airport
Waterways
Cucamonga Creek Channel
Township
T1N
Range
R7W
Section
20
Base
SBBM
Other Information
I-15

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes