City of Livingston Water System Improvement Project
3 Documents in Project
Summary
SCH Number
2017071031
Lead Agency
City of Livingston
Document Title
City of Livingston Water System Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
8/29/2017
Present Land Use
Z: Within existing road ROW
Document Description
City intends to construct and operate a water treatment plant to reduce 1, 2, 3-TCP levels in wells #14 and #16 and a pipeline connecting to the city's existing water distribution system. Construction is anticipated to start in August 2018 and finish in August 2019. Existing water service will not be impacted during construction.
Contact Information
Name
Jose Antonio Ramirez
Agency Name
City of Livingston
Contact Types
Lead/Public Agency
Phone
Location
Cities
Livingston
Counties
Merced
Cross Streets
Olive Ave and Dwight Way
Zip
95334
Parcel #
ROW
State Highways
99
Township
6S
Range
11E
Section
24
Base
MDBM
Notice of Determination
Approving Agency
City of Livingston
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes