Deep Draft Navigation Feasibility Study and Channel Deepening Project

6 Documents in Project

Summary

SCH Number
2016111014
Lead Agency
Port of Long Beach
Document Title
Deep Draft Navigation Feasibility Study and Channel Deepening Project
Document Type
NOD - Notice of Determination
Received
Posted
9/13/2022
Document Description
The Deep Draft Navigation Feasibility Study and Channel Deepening Project (Project) would improve safety and navigation efficiencies for container cargo and liquid bulk vessels at the Port of Long Beach. The Project would deepen the entrance to the Main Channel (the Approach Channel through Queens Gate) from a depth of -76 feet to -80 feet mean lower low water (MLLW); widen portions of the Main Channel (bend-easing) to a depth of -76 feet MLLW; construct an approach channel and turning basin to Pier J South to a depth of -55 feet MLLW; deepen portions of the West Basin and West Basin Approach to a depth of -55 feet MLLW; deepen two additional locations within the harbor to a depth of -55 feet MLLW: the Pier J Slip, including berths J266-J270, and berth T140 on Pier T. Structural improvements would be made to the Pier J breakwaters at the entrance of the Pier J Slip to accommodate deepening of the Pier J Slip and Approach Channel to -55 feet MLLW. To accommodate electric dredging equipment, an electrical substation would be constructed land-side at Pier J. Approximately 7.4 million cubic yards of dredged sediment material generated by the Project would be placed in a nearshore placement site and/or a U.S. Environmental Protection Agency-designated ocean-dredged material disposal site. If construction schedules align, dredged sediment material may be used to fill the Pier G South Slip at the Port.

Contact Information

Name
Justin Luedy
Agency Name
Port of Long Beach
Job Title
Environmental Specialist
Contact Types
Lead/Public Agency

Location

Cities
Long Beach
Counties
Los Angeles
Regions
Citywide, Southern California
Cross Streets
N/A
Zip
90802
State Highways
SR-47, I-710
Railways
Alameda Corridor
Schools
Chavez Elementary School
Waterways
San Pedro Bay, Long Beach Harbor
Other Location Info
Port of Long Beach channels and berths serving Pier J, Pier T/West Basin, the Main Channel, Approach Channel extending seaward from the Queen’s Gate opening of the Long Beach Breakwater

Notice of Determination

Approving Agency
Port of Long Beach
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
www.polb.com/ceqa

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Final Document(s) [Approved_Certified draft environmental documents]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print