Chevron Eureka Terminal Dock Seismic Retrofit

3 Documents in Project

Summary

SCH Number
2016052046
Lead Agency
Humboldt Bay Harbor
Document Title
Chevron Eureka Terminal Dock Seismic Retrofit
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2016
Present Land Use
APN 007-071-013-WD - Development Water & APN 007-071-013 CDI - Coastal Dependent Industrial
Document Description
The Chevron Eureka Terminal Dock seismic retrofit is a compliance driven project as required by the California State Lands Commission per CBC Chapter 31F, Marine Oil Terminals. Retrofitting the structure consists of isolating the pipeway from the timber dock structure by installing a new steel support system along for trestle and a new unloading platform on the wharf. The remainder of the existing dock will remain in place and is not part of this project. Four 24" steel pipe piles will be installed to support the new unloading platform and twenty 16" steel pipe piles will be installed along the trestle to support the pipeway. It is estimated a total of 71 existing treated timber piles will be removed.

Contact Information

Name
George Williamson
Agency Name
Humboldt Bay Harbor
Contact Types
Lead/Public Agency

Location

Cities
Eureka
Counties
Humboldt
Cross Streets
3400 Christie St
Zip
95501
Parcel #
007-071-13, -08
State Highways
101
Waterways
Humboldt Bay, Elk River
Township
5N
Range
1W
Section
33
Base
HB&M

Notice of Determination

Approving Agency
Humboldt Bay Harbor, Recreation and Conservation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print