City of Brentwood - Wastewater Treatment Plant Phase II Expansion Project
5 Documents in Project
Summary
SCH Number
2016052031
Lead Agency
City of Brentwood
Document Title
City of Brentwood - Wastewater Treatment Plant Phase II Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
9/29/2016
Present Land Use
Public Facilities
Document Description
The City of Brentwood is proposing to construct a modular expansion of treatment unit processes for the wastewater treatment plant (WWTP) to increase the treatment capacity from the current 5 million gallons per day to 7.5 MGD to accommodate population growth projected in the City's General Plan. Optional facilities include a new solids dryer for production of Class A biosolids and improvements to the disinfection process. The project would increase recycled water production for landscape irrigation; however, the project would not include construction of additional recycled water distribution facilities at this time.
Contact Information
Name
Jagtar Dhaliwal
Agency Name
City of Brentwood
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Brentwood
Counties
Contra Costa
Cross Streets
City's WWTP on Elkins Way (Sunset Rd nearest cross street)
Zip
94513
Total Acres
4
Parcel #
01822003
Railways
UPRR
Schools
Y
Waterways
Marshe Creek watershed
Township
1N
Range
3E
Section
6
Notice of Determination
Approving Agency
City of Brentwood
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No