Keys Crek Channel Access and Maintenance Project (Streambed Alteration Agreement No. 1600-2016-0111-R5)

2 Documents in Project

Summary

SCH Number
2016041034
Lead Agency
San Diego County
Document Title
Keys Crek Channel Access and Maintenance Project (Streambed Alteration Agreement No. 1600-2016-0111-R5)
Document Type
NOD - Notice of Determination
Received
Posted
8/11/2016
Present Land Use
Limited Ag (A70) and Transportation Corridor (S94)
Document Description
CDFW has executed Streambed Alteration Agreement No. 1600-2016-0111-R5, pursuant to section 1602 of the Fish and GAme Coded to the project applicant, County of San Diego, Dept. of Public Works. The project will construct two access ramps and routinely maintain a portion of Keys Creek immediately upstream of the confluence with the San Luis Rey River. A portion of the project site is a compensatory mitigation area for the Lake Rancho Viejo Development Project (SAA 1600-20004-0157-R5). Two access ramps will be constructed on the west stream bank near the northern and southern termini of the existing concrete low-flow channel. Maintenance activities are described using 5 different tiers of maintenance activities. County engineers will use professional judgment as to the appropriate level of maintenance tier necessary for each maintenance activity based on the estimated accrued sediment in the stream. The project will mitigate project impacts beyond those activities described as Tier 1 as an undermined ratio dependent on the tier of maintenance activities deemed necessary.

Contact Information

Name
Keven Hupf
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Fallbrook
Counties
San Diego
Cross Streets
Dulin Rd and Lake Circle Dr
Zip
92028
Total Acres
8.79
Parcel #
1251002800
State Highways
I-15
Waterways
Keys Creek, San Luis Rey River

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.