Pedro Point Headlands Restoration and Trail Improvement Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2016022068
- Lead Agency
- San Mateo County
- Document Title
- Pedro Point Headlands Restoration and Trail Improvement Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 11/18/2016
- Present Land Use
- San Mateo County: Open Space, RM-CZ/CD; City of Pacifica; Open-Space Residential, A/B-5
- Document Description
- The project is intended to minimize sediment transport to waterways through restoration of areas scarred by past off-road motorcycle use. Restoration would involve the use of erosion and sediment control measures and native landscaping to improve the existing trail network on approx. 32.3 acres at Pedro Point Headlands. The project would involve filling and eliminating gullies and trail scares; reestablishing natural topography and positive drainage; restoring disturbed trails and gullies; propagating and salvaging native plants; and, decommissioning unsafe trail segments.
- Contact Information
-
Christian Murdock
City of Pacifica
Lead/Public Agency
1800 Francisco Blvd.
Pacifica, CA 94044
Phone : (650) 738-7341
Location
- Cities
- Pacifica
- Counties
- San Mateo
- Cross Streets
- Highway 1
- Zip
- 94044
- Total Acres
- 32.3
- Parcel #
- 023-730-020, 040, 210, 220; 023
- State Highways
- 1
- Schools
- Linda Mar. Edu. Center
- Waterways
- San Pedro Creek
Notice of Determination
- Approving Agency
- Planning Commission of the City of Pacifica
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- 1800 Francisco Blvd., Pacifica, CA 94044
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.