Local Resources Program Agreement with the El Toro Water District for the El Toro Recycled Water System Expansion Phase II Project

4 Documents in Project

Summary

SCH Number
2016011034
Lead Agency
El Toro Water District
Document Title
Local Resources Program Agreement with the El Toro Water District for the El Toro Recycled Water System Expansion Phase II Project
Document Type
NOD - Notice of Determination
Received
Posted
12/14/2016
Present Land Use
Land Use: Local Streets: Zoning: No designation/Residential Community; GP: No designation/Adult Single and Multiple Family
Document Description
ETWD is proposing to expand the existing Recycled Water Distribution System to allow for delivery of up to 300 acre feet per year of additional tertiary-treated recycled water to existing dedicated irrigation customers within the ETWD service area. The proposed project would include construction of approx. 28,500 feet or 5.4 mile of recycled water pipelines beneath existing roadways.

Contact Information

Name
Dennis Cafferty
Agency Name
El Toro Water District
Contact Types
Lead/Public Agency

Location

Cities
Laguna Woods
Counties
Orange
Cross Streets
El Toro Road, Via Carrizo, Monte Hermoso, Paseo De Valencia, and Avenida De La Carlota
Zip
92637
Total Acres
5.4
Parcel #
Various
State Highways
I-5
Schools
San Joaquin Elem.
Waterways
Veeh Reservoir
Township
6S
Range
7W
Section
9
Base
SB

Notice of Determination

Approving Agency
El Toro Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.