Sacramento International Airport Solar PV Project

2 Documents in Project

Summary

SCH Number
2015112036
Lead Agency
Sacramento County
Document Title
Sacramento International Airport Solar PV Project
Document Type
NOD - Notice of Determination
Received
Posted
4/7/2016
Present Land Use
Within Sacramento International Airport Operations Area/AG-80/Public Quasi-public
Document Description
The proposed project consists of the installation of two alternating current photovoltaic (PV) generation facilities totaling 6.5 megawatts ("North Site" and "East Site") in the Airport operations area. The North Site will be located on 30 acres, with solar arrays encompassing approx. 20 acres. The East Site will be located on 26 acres, with solar arrays encompassing approx. 17 acres. Upon completion, the North Site and East Site (collectively, "Project") will provide electric power to the Sacramento International Airport. Construction for the project is anticipated to last seven months over three phases: site preparation; system installation; and system testing, commissioning and cleanup. Construction will occur simultaneously on the two sites with up to fifty workers on the project-wide site at any given time. Site preparation will involve preparing the land for installation of arrays, related infrastructure, ingress-egress points, and temporary construction staging areas. The North Site will require land grubbing on approx. 2 acres. The remainder of the site is an existing parking lot and requires little preparation. System installation requires pile driving, trenching for electrical conduits, and some underground boring for conduits. The Project will utilize existing roads within the Airport for construction access and routine maintenance. Erection of the solar arrays will include installing support structures and associated electrical equipment; including I-beams, or "standards" are typically spaced 26' along the row and 12.5' between the rows and installed to a height above ground of approx. 5 feet. The top of the PV module will be approx. 7 feet above grade when at full tracking angle. Once the standards have been installed, the horizontal cross-members of the single-axis tracking system and associated motors will be placed and secured. A galvanized metal racking system, which holds the PV modules in the correct position for maximum capture of solar energy, are then assembled and attached to the horizontal cross members. The arrays will consist of a single-axis tracking system. Trenching along approx. 2,000 feet will be required to install the necessary electrical hookups to the Sacramento Municipal Utility District (SMUD) facilities. During testing, commissioning , and clean-up, on-site activity will be limited to a few technical experts. Once operational, it is anticipated that two to five people will be onsite up to twice per year for one week for regular maintenance and panel washing.

Contact Information

Name
Catherine Hack
Agency Name
Sacramento County
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
Airport Blvd/I-5
Zip
95837
Total Acres
56
Parcel #
201-023-0034 201-023-0044, 201-023-0045
State Highways
I-5, Hwy 99
Airports
Sacramento International Airport
Waterways
Sacramento River
Township
10N
Range
4E
Section
19,30
Base
USGS

Notice of Determination

Approving Agency
County of Sacramento
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes