Temple Hills Drive Sidewalk Project

2 Documents in Project

Summary

SCH Number
2015111054
Lead Agency
City of Laguna Beach
Document Title
Temple Hills Drive Sidewalk Project
Document Type
NOD - Notice of Determination
Received
Posted
6/1/2016
Present Land Use
Right-of-way/Village Low Density/R-1; Residential Low Density Zoning District
Document Description
The City of Laguna Beach is proposing the construction of a sidewalk along an approx. 0.5 mile stretch of Temple Hills Drive as part of the City's Capital Improvement Program. The proposed improvements would start at Palm Drive, terminate Dunning Drive, and be built on land owned by the City of Laguna Beach. The proposed project would include installation of a four foot sidewalk and associated curb and gutter along the east/southeast side of Temple Hills Drive. Approx. 10,560 sq. ft. of sidewalk would be installed in total. The project would require verification of right-of-way construction of the sidewalk, reconstruction of driveway approaches to meet City standards, installation of curbs and gutters, installation of curb ramps, storm drain improvements, and reconstruction of some private improvements.

Contact Information

Name
Tom Sandefur
Agency Name
City of Laguna Beach
Contact Types
Lead/Public Agency

Location

Cities
Laguna Beach
Counties
Orange
Cross Streets
Along Temple Hills Drive between Dunning Drive and of Palm Drive
Zip
92551
Total Acres
24
State Highways
CA-SR 133/SR 1
Waterways
Pacific Ocean
Township
7S
Range
9W
Section
24,25
Base
SBBM

Notice of Determination

Approving Agency
City of Laguna Beach
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.