Concurrence in issuance of Revised Solid Waste Facilities Permit (SWFP) for Victor Valley Materials Recovery Facility & Transfer Station, SWIS No. 36-AA-0346
3 Documents in Project
Summary
SCH Number
2015101108
Lead Agency
City of Victorville
Document Title
Concurrence in issuance of Revised Solid Waste Facilities Permit (SWFP) for Victor Valley Materials Recovery Facility & Transfer Station, SWIS No. 36-AA-0346
Document Type
NOD - Notice of Determination
Received
Posted
5/21/2020
Present Land Use
Specific Plan
Document Description
Increasing total acreage from 13.7 to 18.57 acres; increasing total maximum daily tonnage from 600 to 1,235 tons per day; changing hours of operation to 24 hours per day, 7 days per week for all activities; changing the design capacity from 500 tons per day (transfer/processing) to 1,235 tons per day (1,135 tons per day transfer/processing and 100 tons per day composting); addition of food waste and CDI wastes as acceptable materials; addition of a 100 ton per day aerated static pile compost facility; addition of a 8,000 square foot food waste receiving building; addition of a 3.6-acre organics processing area; construction of a new entrance at the southwest corner of the facility; construction of a new driveway at the northeast corner of the facility; addition of a new scale house to the new entrance driveway; installation of two storm water detention basins; addition of a 16,000 square foot CDI sorting facility; increasing total facility personnel from 35 to 89; increasing permitted traffic volume from 96 to 269 vehicles per day; and updating the Transfer/Processing Report and adding a Report of Composting Site Information.
Contact Information
Name
Megan Emslander
Agency Name
CalRecycle
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Burrtec Waste Industries, Inc.
Contact Types
Project Applicant
Location
Cities
Victorville
Counties
San Bernardino
Cross Streets
17000 Abbey Lane, Victorville
Zip
92394
Notice of Determination
Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No