Construction & Operation of a New Transmission Pipeline & Chromium 6 Treatment Plant
4 Documents in Project
Summary
SCH Number
2015062021
Lead Agency
Soquel Creek Water District
Document Title
Construction & Operation of a New Transmission Pipeline & Chromium 6 Treatment Plant
Document Type
NOD - Notice of Determination
Received
Posted
12/14/2016
Present Land Use
Public and Community Facilities, public right-of-way
Document Description
The SWRCB, as the responsible agency, will be issuing a water supply permit. The Soquel Creek Water District, as the lead agency, will construct a new raw water pipeline from the District's Seascape well to the San Andreas well within the County right of way. This pipeline, with the help of an existing pipeline between the San Andreas well and the Bonita well, will deliver groundwater to a 2,000 gpm chromium 6 water treatment facility that will be constructed and include a pre-filtration, SBA-IX treatment system area, an electrical and control room, a chemical feed area, a restroom, and roll up doors. The regeneration system will include an 8,800 gallon brine/salt storage tank, a brine pump skid, and a vessel. The building will also house potential brine reduction technology.
It is estimated 50,000 gallons of waste will be generated annually. Any Chromium-6 above 5 mgL will be hauled by a licensed hazardous waste hauler to a hazardous waste site. it is estimated that up to 40,000 gallons annually may be converted to a nonhazardous form which may be disposed of via sanitary sewer. A 300 kilowatt standby generator will also be installed at the site in an enclosure to reduce sound. Three 1,000 gpm 200 HP groundwater pumps at the Seascape well and the San Andres well, will be replaced, given the need, as a result of changes in pressure. The PG&E transformers and service lines will be upgraded at both sites. Cabinets and a steel enclosure for electrical services will also be replaced at teh Seascape well site. A new sewer main will be installed to run from the treatment facility to the Santa Cruz Sanitation District sewer system to dispose of wastewater and treated brine waste from the Project. The treatment facility will insure the drinking water is below the maximum contaminant level of 10 micrograms/liter for chromium 6. A new stormwater detention basin will also be installed, as required. The project will provide for the operation of these facilities.
Contact Information
Name
Jan Sweigert
Agency Name
SWRCB
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Santa Cruz
Cross Streets
Bonita Drive and San Andreas Road
Zip
95003
Total Acres
.96
Parcel #
053-131-17
State Highways
Hwy 1
Railways
SPRR
Schools
St. Abraham's Classical
Waterways
Pacific Ocean
Township
11S
Range
1E
Section
7
Other Location Info
Aptos
Notice of Determination
Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.