Harkins Bridge Replacement Project

3 Documents in Project

Summary

SCH Number
2014102044
Lead Agency
Midpeninsula Regional Open Space District
Document Title
Harkins Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
9/14/2015
Present Land Use
Timberland Preserve-Coastal Zone District (TPZ-CZ)
Document Description
The project entails the removal of an existing bridge, installation of a replacement bridge and restoration of the riparian banks at the old bridge location on Purisima Creek, approximately 100 yds east of the intersection of Higgins Canyon Road and Purisima Creek Road on the Whittemore Gulch Trail within the Purisima Creek Open Space Preserve in San Mateo County. The new bridge will be installed approximately 100 ft upstream of the existing bridge and will be a 60-ft long by 15-ft wide prefabricated steel bridge with structural concrete abutments. It will serve as a crossing for patrol, fire and other emergency vehicles. A temporary culvert crossing with an associated water diversion will be installed and a new access roadway and trail to the proposed bridge will be constructed. The existing bridge location will be restored with native vegetation and new biotechnically stabilized slopes. CDFW is executing a lake and streambed alteration agreement, no 1600-2015-0079-R3, pursuant to section 1602 fish and game code to the project permittee, Midpeninsula Open Space District.

Contact Information

Name
Suzanne DeLeon
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Half Moon Bay
Counties
San Mateo
Cross Streets
Higgins Canyon Road and Purisima Creek Road
Zip
94019
Total Acres
.08
Parcel #
067-320-220
State Highways
Hwy 1
Waterways
Purisima Creek
Township
6S
Range
5W
Section
1

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.