Addendum to the Avalon Freight Services Final Initial Study and Negative Declaration

4 Documents in Project

Summary

SCH Number
2014101049
Lead Agency
Port of Los Angeles
Document Title
Addendum to the Avalon Freight Services Final Initial Study and Negative Declaration
Document Type
NOD - Notice of Determination
Received
Posted
11/18/2021
Document Description
The proposed Project would upgrade the barge landing ramp at Berth 95 to fix the ramp design and improve barge access. Improvements to the ramp would allow Avalon Freight to utilize the ramp with the same frequency, but on a preferred schedule not dependent on tides. The barge landing ramp upgrades include demolition and removal of approximately 5,000 square feet of in-water concrete ramp, dredging and disposal of approximately 3,000 cubic yards of sediment, furnishing and placing approximately 850 tons of quarry run and rip rap, and casting in place of an approximately 400 square-foot concrete approach slab. The proposed modifications would create no potential adverse impacts or substantial changes to impact areas previously analyzed in the Final IS/ND.

Contact Information

Name
Leah Kohler
Agency Name
Port of Los Angeles
Job Title
Environmental Specialist
Contact Types
Lead/Public Agency

Location

Cities
San Pedro
Counties
Los Angeles
Regions
Citywide
Zip
90731
Other Location Info
Berth 95

Notice of Determination

Approving Agency
Los Angeles Harbor Department
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
portoflosangeles.org/environment/environmental-documents

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Final Document(s) [Approved_Certified draft environmental documents]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print