Sunnyside Estates Removal Action Workplan

5 Documents in Project

Summary

SCH Number
2014091018
Lead Agency
San Benito County
Document Title
Sunnyside Estates Removal Action Workplan
Document Type
NOD - Notice of Determination
Received

Document Description
Project consists of approval by the DTSC of a Removal Action Workplan for the Sunnyside Estates site. DTSC's approval action is being undertaken pursuant to the regulatory authority granted under Chapter 6.8, Division 20 of the Health and Safety Code. The purpose of the RAW, which constitutes the project subject to approval by the DTSC, is to mitigate potential risk to human health and the environment from the contaminants of concern (COCs) in soil: arsenic lead, dieldrin, and DDE/DDT/DDD. The Site is being developed as a community with single-family residential units, a 3-acre park, landscaping, and private streets. Removal activities to be conducted pursuant to the RAW include the following: Excavate an estimated 3,000 cubic yards of COCs-impacted soil from locations previously identified during Site investigations; Approx. 500 cubic yards of the excavated contaminated soil will be disposed at a permitted facility. The remaining 2,500 cubic yards of soil will be consolidated below the utility zone beneath future paved roads.

Contact Information
Nicole Yuen
DTSC
700 Heinz Ave.
Berkeley, CA 94702

510-540-3881

Location

Coordinates
36°49'15"N 121°23'28"W
Cities
Hollister
Counties
San Benito
Cross Streets
Southside Road and Hospital Road
Zip
95023
Total Acres
44.4
Parcel #
Multiple
State Highways
Hwy 25
Schools
Multiple
Waterways
San Benito River
Township
13S
Range
5E
Section
11

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
https://www.envirostor.dtsc.ca.gov/public/profile_report.asp?global_id=60002575

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes