Soquel Pump Station Force Main Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/26/2014
Present Land Use
Z: PF, CC, PF-F/P GPD: PF, CC, R-M
Document Description
The project is limited to the installation of a new 24-inch transmission main from the Soquel Creek Pump Station to the existing discharge in Clares Road, just west of Wharf Road. The new transmission main will be made of High Density Polyethylene (HDPE) and will be approximately 1,200 linear feet long. Approximately 860 feet will be constructed using horizontal directional drilling (HDD) installation methods and 340 linear feet will be constructed using traditional open trench methods. An additional 70 linear feet of new 30-inch gravity pipeline will be installed using open trench construction methods in Clares Street. The pipeline will run for approximately 60 feet under Soquel Creek, approximately 40 feet below the bed of the creek. The California Department of Fish and Wildlife is executing a Lake and Streambed Alteration Agreement Number 1600-2014-0224-R3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Rachel Lather, Santa Cruz Sanitation District.

Contact Information

Name
Melissa Farinha
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Capitola
Counties
Santa Cruz
Cross Streets
Clares Street/Wharf Road, Bay Avenue
Zip
95010
Total Acres
1
Parcel #
035-020-042, 035-370-001
State Highways
Hwy 1
Schools
Soquel ES
Waterways
Soquel Creek, Monterey Bay / Soquel Cove
Township
11S
Range
1W
Section
15
Base
MDB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A