Soquel Pump Station Force Main Replacement Project

4 Documents in Project

Summary

SCH Number
2014052085
Lead Agency
Santa Cruz County Sanitation District
Document Title
Soquel Pump Station Force Main Replacement Project
Document Type
NOD - Notice of Determination
Received

Document Description
The Soquel Pump Station Force Main Replacement Project involves the installation of a new force main underneath Soquel Creek in Capitola, California between Wharf Road and Bay Avenue. The existing 27-inch force main crossing was constructed in 1977 and if deterioration were to occur in the Soquel Creek transmission main, it could have an adverse effect on the environment. The new force main would be installed from the Soquel Pump Station to the existing sanitary sewer pipeline in Clares Street and will be installed using a combination of trenchless and open trench construction methods to replace the deteriorated transmission main. The project also includes various mechanical upgrades to the Soquel Pump Station to enhance the operational reliability of the pump station. The project will take approximately 5.5 months to complete.

Contact Information
Rachel Lather
Santa Cruz County Sanitation District
701 Ocean Street, Room 410
Santa Cruz, CA 95060

831-454-2637

Location

Coordinates
36°58'41.08"N 121°57'27.82"W
Cities
Capitola
Counties
Santa Cruz
Cross Streets
Clares Street/Wharf Road, Bay Avenue
Zip
95010
Total Acres
1
Parcel #
035-020-042, 035-370-001
State Highways
Hwy 1
Schools
Soquel ES
Waterways
Soquel Creek, Monterey Bay / Soquel Cove
Township
11S
Range
1W
Section
15
Base
MDB&M

Notice of Determination

Approving Agency
Santa Cruz County Sanitation District
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
701 Ocean Street, Room 410, Santa Cruz, CA 95060

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes