Soquel Pump Station Force Main Replacement Project

4 Documents in Project

Summary

SCH Number
2014052085
Lead Agency
Santa Cruz County Sanitation District
Document Title
Soquel Pump Station Force Main Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
8/13/2014
Present Land Use
Z: PF, CC, PF-F/P GPD: PF, CC, R-M
Document Description
The Soquel Pump Station Force Main Replacement Project involves the installation of a new force main underneath Soquel Creek in Capitola, California between Wharf Road and Bay Avenue. The existing 27-inch force main crossing was constructed in 1977 and if deterioration were to occur in the Soquel Creek transmission main, it could have an adverse effect on the environment. The new force main would be installed from the Soquel Pump Station to the existing sanitary sewer pipeline in Clares Street and will be installed using a combination of trenchless and open trench construction methods to replace the deteriorated transmission main. The project also includes various mechanical upgrades to the Soquel Pump Station to enhance the operational reliability of the pump station. The project will take approximately 5.5 months to complete.

Contact Information

Name
Rachel Lather
Agency Name
Santa Cruz County Sanitation District
Contact Types
Lead/Public Agency

Location

Cities
Capitola
Counties
Santa Cruz
Cross Streets
Clares Street/Wharf Road, Bay Avenue
Zip
95010
Total Acres
1
Parcel #
035-020-042, 035-370-001
State Highways
Hwy 1
Schools
Soquel ES
Waterways
Soquel Creek, Monterey Bay / Soquel Cove
Township
11S
Range
1W
Section
15
Base
MDB&M

Notice of Determination

Approving Agency
Santa Cruz County Sanitation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print