Plant 3A Effluent Transmission Main Replacement Project MNWD Project 2009.115

2 Documents in Project

Summary

SCH Number
2014051023
Lead Agency
Moulton Niguel Water District (MNWD)
Document Title
Plant 3A Effluent Transmission Main Replacement Project MNWD Project 2009.115
Document Type
NOD - Notice of Determination
Received
Posted
7/28/2014
Present Land Use
PLU: Channelized San Juan Creek Z: General Open Space GPD: General Open Space
Document Description
A 30-inch diameter, 298-foot long treated effluent pipeline is proposed to be installed via microtunneling beneath the concrete channelized San Juan Creek as a replacement for MWND's Plant 3A effluent transmission main (ETM) under co-ownership with Santa Margarita Water District (SMWD). Construction would last approximately nine weeks, beginning in November 2014, and would be limited to the two staging areas and pits on the north and south side of San Juan Creek. Operation of the proposed project would be entirely underground with the exception of occasional maintenance.

Contact Information

Name
Nancy Baker
Agency Name
Moulton Niguel Water District
Contact Types
Lead/Public Agency

Location

Cities
San Juan Capistrano
Counties
Orange
Cross Streets
Calle Perfecto and Paseo Toscana
Zip
92675
Parcel #
Various
State Highways
I-5
Railways
Burlington Northern Santa Fe
Schools
Del Obispo ES and Marco Foster MS
Waterways
San Juan Creek and Trabuco Creek

Notice of Determination

Approving Agency
Moulton Niguel Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.