San Luis Transmission Project

6 Documents in Project

Summary

SCH Number
2013112059
Lead Agency
San Luis and Delta Mendota Water Authority
Document Title
San Luis Transmission Project
Document Type
NOD - Notice of Determination
Received
Posted
11/3/2021
Document Description
New 500-kV 65 mile transmission line between the new Tracy East and Los Banos West Substation; 3-mile 230-kV transmission line between PG&E Los Banos Substation to new Los Banos West Substation and Western's San Luis Substation; 20-mile 230-kV transmission line between Western's San Luis and Dos Amigos Substations or a new 18-mile 230 kV transmission line between the new Los Banos West Substation and Western's Dos Amigos Substation; and interconnection with Western 500-kV Los Banos Gates No. 3 transmission line into the new Los Banos West Substation; 7-mile 70-kV transmission line between the existing San Luis and O'Neill Substations.

Contact Information

Name
Lon Martin
Agency Name
San Luis Water District
Contact Types
Responsible Agency

Location

Counties
Fresno, Merced
Other Location Info
Alameda, Stanislaus, San Joaquin and Merced Counties

Notice of Determination

Approving Agency
San Luis Water District
Approving Agency Role
Responsible Agency
Approved On
County Clerks
Fresno, Merced
Final Environmental Document Available at
San Luis Water District, 1015 6th St., Los Banos CA 93635

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.