Main Camp to Fairfield a 6-inch and 8-inch Pipelines (California Endangered Species Act Incidental Take Permit No. 2081-2017-035-04 (ITP))

631 Documents in Project

Summary

SCH Number
2013081079
Lead Agency
Kern County
Document Title
Main Camp to Fairfield a 6-inch and 8-inch Pipelines (California Endangered Species Act Incidental Take Permit No. 2081-2017-035-04 (ITP))
Document Type
NOD - Notice of Determination
Received

Document Description
Project will be constructing an above-ground 6-inch natural gas pipeline and an above ground 8 inch water pipeline from the Kern/Mojave pipeline connection, near the Fairfield lease in Section 11, to the Main Camp lease in the southeast quarter of Section 24. The pipelines will be approx. 3.62 miles in length. The project will result in permanent impacts to 0.052 acres and temporary impacts to 8.656 acres of habitat. The project is expected to result in incidental take of San Joaquin kit fox (Vulpes macrotis mutica), San Joaquin antelope squirrel (Ammospermophilus nelson), which are designated as a threatened species under the CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information
Benessa Espino
CDFW
1234 E. Shaw Ave.
Fresno, CA 93710

559-243-4014

Location

Counties
Kern
Zip
93560
Total Acres
3110 sq mi
Parcel #
Multiple
State Highways
Hwy 99, 58, 43, 46, 119, 223, 20
Railways
Multiple
Airports
Multiple
Schools
Multiple
Waterways
Kern River
Other Location Info
Multiple

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
1234 E. Shaw Ave., Fresno, CA 93710

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes