Main Camp to Fairfield a 6-inch and 8-inch Pipelines (California Endangered Species Act Incidental Take Permit No. 2081-2017-035-04 (ITP))

4119 Documents in Project

Summary

SCH Number
2013081079
Lead Agency
Kern County
Document Title
Main Camp to Fairfield a 6-inch and 8-inch Pipelines (California Endangered Species Act Incidental Take Permit No. 2081-2017-035-04 (ITP))
Document Type
NOD - Notice of Determination
Received
Posted
11/21/2017
Present Land Use
Developed and Undeveloped land in Kern County. Current Zoning Classifications and General Plan Map Code Designations to remain the same.
Document Description
Project will be constructing an above-ground 6-inch natural gas pipeline and an above ground 8 inch water pipeline from the Kern/Mojave pipeline connection, near the Fairfield lease in Section 11, to the Main Camp lease in the southeast quarter of Section 24. The pipelines will be approx. 3.62 miles in length. The project will result in permanent impacts to 0.052 acres and temporary impacts to 8.656 acres of habitat. The project is expected to result in incidental take of San Joaquin kit fox (Vulpes macrotis mutica), San Joaquin antelope squirrel (Ammospermophilus nelson), which are designated as a threatened species under the CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Benessa Espino
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Counties
Kern
Zip
93560
Total Acres
3110 sq mi
Parcel #
Multiple
State Highways
Hwy 99, 58, 43, 46, 119, 223, 20
Railways
Multiple
Airports
Multiple
Schools
Multiple
Waterways
Kern River
Other Location Info
Multiple

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.