Guru Nanak Singh Temple Water Line Extension

2 Documents in Project

Summary

SCH Number
2013042030
Lead Agency
City of Fairfield
Document Title
Guru Nanak Singh Temple Water Line Extension
Document Type
NOD - Notice of Determination
Received
Posted
5/20/2013
Present Land Use
Solano County Agriculture
Document Description
The project will provide potable City of Fairfield drinking water to an existing Sikh temple located in unincorporated Solano County. Existing domestic water from the on-site well has become contaminated and constitutes a public health hazard. A 3" diameter HDPE water line will be constructed within the Rockville Road and/or within City of Fairfield property no closer than two feet from the existing pavement but within the graded roadway. The total length of the water line will be 2,222 feet. The water line will be extended from an existing service interconnection just east of Ledgewood Creek for 1,525 feet along the north side of Rockville Road, then cross under Rockville Road to the south side onto the parcel owned by the Temple. For approximately 80 feet, the pipeline will encased in a steel casing attached to the north side of the existing bridge over Ledgewood Creek.

Contact Information

Name
Karen Weiss
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
Rockville Road
Zip
94585
Parcel #
multiple
State Highways
I-80, SR 12
Railways
UPRR
Airports
No
Schools
No
Waterways
Ledgewood Creek, Suisun Valley Creek, Suisun Marsh

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print