North Lane Stormwater Mitigation Project No. 4070

3 Documents in Project

Summary

SCH Number
2012082004
Lead Agency
City of Orinda
Document Title
North Lane Stormwater Mitigation Project No. 4070
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2014
Present Land Use
Residential low Density (RL-20, 20,000 sf), Residential: Single-Family Low Density (1-2 units/ac), Utility (PS)
Document Description
The project was proposed because of previous flooding that cascaded over Camino Pablo and into the East Bay Municipal Utility District (EBMUD) water treatment plant during storm event. Existing 48" culverts and ditches overflowed. The project involves (1)construction of a new upstream headwall; (2)construction by open trench of 60" storm drain pipe in North Ln for approx. 900'; (3)jack and bore a 60" pipe for approx. 310' across Camino Pablo to the EBMUD treatment plant property; (4)jack and bore a 60" pipe approx. 90' from EBMUD treatment plant property to San Pablo Creek; (5)construction at San Pablo Creek of a new discharge headwall; and (6)placement of rock slope.

Contact Information

Name
Lawrence Theis
Agency Name
City of Orinda
Contact Types
Lead/Public Agency

Location

Cities
Orinda
Counties
Contra Costa
Cross Streets
Camino Pablo, North Lane, Ardilla Road
Zip
94563
Total Acres
.6
Parcel #
263110004, 264130019
State Highways
Hwy 24
Schools
Wagner Ranch ES
Waterways
San Pablo Creek
Township
1N
Range
3W
Base
MDB&M

Notice of Determination

Approving Agency
City Council of the City of Orinda
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.