Eastside Water Banking and Blending Project

4 Documents in Project

Summary

SCH Number
2012081073
Lead Agency
Antelope Valley-East Kern Water Agency (AVEK)
Document Title
Eastside Water Banking and Blending Project
Document Type
NOD - Notice of Determination
Received
Posted
5/14/2014
Present Land Use
LU: Undeveloped Z: O-S, A-2-1 GPD: Non-Urban
Document Description
AVEK proposes to construct and operate a water banking and blending project that would involve spreading State Water Project raw water into recharge basins in order to bank a portion of the SWP water for extraction as an alternative potable groundwater supply for periodic substitution or supplement to the Eastside Water Treatment Plant. Three 2-acre recharge basins, four extraction wells, and associated facilities would be constructed on the project site. In addition, pipelines would be installed under East Avenue U, 96th Street East, and 116th Street east. Modification also would be made to the 96th Street East Turnout of the California Aqueduct.

Contact Information

Name
Michael Flood
Agency Name
Antelope Valley-East Kern Water Agency
Contact Types
Lead/Public Agency

Location

Counties
Los Angeles
Cross Streets
116th Street East and East Avenue U
Zip
93553
Total Acres
80
Parcel #
3039-029-908, 3039-029-027
State Highways
SR 138
Railways
No
Airports
No
Schools
No
Waterways
CA Aqueduct
Township
5N
Range
10W
Section
15/16
Base
SBB&M
Other Location Info
City/Nearest Community: Pearblossom

Notice of Determination

Approving Agency
Antelope Valley-East Kern Water Agency (AVEK)
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print